Eagle Gold

Layfield Enters Final Phase of Eagle Gold Project

Company News

In 2019, Layfield began the final phase of a multiyear geosynthetics installation project with Victoria Gold Corp. The Eagle Gold project is located approximately 85km by road northeast of the Village of Mayo, Yukon.

This installation consisted of four separate project scopes, commencing in 2017 with a 24,730m2 Control Pond. The Control Pond was comprised of two separate layers; LP12 geotextile underlay and 60 mil Tex 2 LLDPE geomembrane. In 2018, Layfield installed a 62,000m2 In Heap Pond consisting of four layers. This system included NWL60 GCL, 60 mil Tex 2 LLDPE geomembrane, 350-2-6 Geocomposite, and 80 mil Tex-2 LLDPE geomembrane.

This year’s phase of the project included the installation of a four-layer 53,000m2 Event Pond and a two-layer 169,000m2 Heap Leach Pad. During this phase, our crew has installed more than 50 acres each of NWL60 GCL and 80 mil Tex 2 LLDPE geomembrane and close to 13 Acres each of 60 mil Tex 2 LLDPE geomembrane and 220-2-8 Geocomposite.

The crew has worked fastidiously on each phase while maintaining Layfield’s high level of safety standards and will finish up this year ahead of schedule. We extend our thanks to Victoria Gold Corp for trusting Layfield for their liner needs and look forward to working with them in the future.

If you’d like to learn more about the Victoria Gold Project (Eagle Gold) and view some of the Layfield liner projects in action, check out the Victoria Golf promotional video.  

Related Articles

View All News
August 10, 2023 Employee Spotlight — Jan Nichols, Regional Sales Manager Read Article
August 3, 2023 Transforming Lake Forest Reservoir: A Relining and Floating Cover Project Read Article
July 18, 2023 Employee Spotlight — Rohit Sati, Technical Product Manager Read Article
July 5, 2023 Alex Gersch Promoted to Director of Layfield Australia, Showcasing Expertise in the Geosynthetic Industry Read Article
June 28, 2023 Biofilter Rehabilitation at Toronto’s Humber Wastewater Treatment Plant Read Article
June 27, 2023 Premature Failure of Geomembrane Floating Covers in Australia: Causes, Comparisons, and Recommendations Read Article
June 16, 2023 Employee Spotlight | Michael Corbett, Vice President of Sales and Operations Read Article
May 3, 2023 Pittsburgh Water & Sewer Authority announced Layfield was awarded the Highlands 2 Reservoir Read Article
March 23, 2023 Layfield’s Edmonton Facility was granted accreditation by the Geosynthetic Institute Read Article
Technical-Paper-Presentation-Rohit-Sati
March 22, 2023 Layfield Presents Multiple Technical Papers at 2023 Geosynthetics Conference Read Article

Find the Product You Need? Reach out to Our Team.

Click the link below to get in touch with us, and our team will get back to you promptly.